Here is a rough schedule we have been provided with:
September 10: Start date: Install tree protection, erosion barrier, and begin tree/brush removal
September 12: Begin site demolition to include asbestos, underground storage tank, buildings, fence, sidewalk and curbs
September 25: Begin storm sewer layout and installation
October 6 – November 7: Site grading and construction of curbs, walks, landscaping wall, etc. November 12: Begin paving operations
November 21-25: Install fencing
November 26: Painting
March 2: Landscaping